2026-11-20
Germany to close A99 near Munich for 57 hours, with long-distance diversions for trucks

The A99 motorway on Munich’s eastern ring road will be completely closed in both directions from Friday, 20 November 2026, at 8:00 p.m. until Monday, 23 November, at 5:00 a.m. The closure is necessary to demolish a bridge carrying the B304 road near the Haar interchange. Autobahn GmbH is warning of major disruption across the region and recommends that trucks use long-distance alternative routes.
The closure will affect the section between the München-Süd and München-Ost motorway interchanges. Preparations for the closure will begin on Friday at 6:00 p.m., and traffic will be completely stopped two hours later. The demolition, including preparatory and clearance work, will continue around the clock without interruption.
Disruption across the Munich region
Autobahn GmbH expects a significant increase in traffic in Munich and the surrounding districts of Munich, Ebersberg and Erding. Both urban roads and alternative routes will face additional pressure, including the B304, B471, A94, the western section of the A99 and the B15 between Rosenheim and Landshut.There is no single diversion route capable of handling all the traffic from the closed section. The motorway operator therefore warns that major alternative roads may also become congested and recommends avoiding the region altogether.
During the works, Munich will temporarily suspend the truck and diesel vehicle traffic ban on the Mittlerer Ring (B2R), except for the section between the A9 and A96 motorway interchanges.
Long-distance diversions for trucks
Long-distance alternative routes have been prepared for trucks and will be signposted well in advance of Munich. Autobahn GmbH recommends the following routes:▪️ From Würzburg: via the A7 and A96 motorways through Memmingen and Lindau, then through the Arlberg Tunnel towards the Brenner Pass.
▪️ From Nuremberg: diversion via Linz.
▪️ From the Inntaldreieck interchange and Salzburg: also via Linz.
The diversion signs are intended to direct some of the traffic away from Munich before vehicles reach the congested roads in the region.
Demolition of the B304 bridge
The closure is necessary because of the poor technical condition of a bridge built in 1973, which carries the B304 over the A99 near the Haar interchange. The structure is seriously damaged and cannot be permanently repaired. Due to the risk of the remaining part of the bridge losing stability during demolition, the work cannot be carried out in stages. The entire bridge will be demolished in one continuous operation.Traffic on the B304 has already been transferred to a specially built temporary bridge, which will remain open during the demolition of the old structure. A new bridge will be built in its place, with the entire project scheduled for completion in December 2028.